NLC India plans to develop a 1.4 GW nuclear power plant with Nuclear Power Corporation of India Ltd (NPCIL), with the project estimated to cost up to Rs 35,000 crore, the company’s chairman and managing director, Prasanna Kumar Acharya, has said.
The proposed plant will comprise two units of around 700 MW each. The two companies signed a memorandum of understanding on 25 May 2026 to form a joint venture for developing nuclear power projects, and the joint venture agreement is expected to be signed by the end of this financial year.
“We are expecting that by the end of this financial year, we will be able to sign the joint venture agreement and form the JV company. NPCIL is identifying the sites, and once the location is finalised, we can take the project forward,” Acharya told Moneycontrol in an exclusive interview.
What the project will cost
The estimate is based on the current cost of nuclear power projects of around Rs 20 to 25 crore per MW, which puts the 1.4 GW plant at a total investment of Rs 28,000 to 35,000 crore.
NPCIL, a public sector enterprise under the Department of Atomic Energy, is responsible for the design, construction, commissioning and operation of nuclear power reactors. It currently operates all 24 commercial nuclear power reactors in India, with an installed capacity of 8.78 GW.
For NLC India, a Navratna public sector company based in Neyveli, Tamil Nadu, and best known for lignite mining and thermal power, the project marks a step into a new line of business and would add a large, steady source of low-carbon electricity to its portfolio.
Other partnerships on the table
NLC has also started discussions with French energy major EDF, but no agreement has been finalised.
“We have just started discussing with EDF. We will further explore other possibilities. We have not finalised anything on that,” Acharya said. He said the company was not in talks with Russian entities for nuclear power projects.
The interest reflects how the sector is opening up. The National Nuclear Energy Mission, announced in the Union Budget 2025-26, aims to expand nuclear power as a source of reliable, low-carbon electricity, and the SHANTI Act, 2025, has enabled wider participation by public and private sector companies.
India’s 100 GW nuclear target
The project comes as India seeks to raise nuclear capacity to 100 GW by 2047 from the current 8.78 GW. The roadmap sees about 22 GW by 2031-32, with NPCIL adding 32 GW more to reach around 54 GW. The remaining 46 GW is expected from other public sector enterprises, state governments, private companies and joint ventures.
The government has also set a target to operationalise at least five indigenous small modular reactors by 2033.
Why this deal matters for NLC
– It gives NLC a foothold in nuclear power, a sector set to grow sharply as India works towards 100 GW by 2047. – The joint venture structure shares the cost and the execution risk with NPCIL, which operates every commercial reactor in the country. – A two-unit plant of 700 MW each fits the scale at which NPCIL builds, which should help with licensing, construction and operations. – The Rs 35,000 crore investment would be one of the largest single projects in NLC’s history.
The next step is the site. NPCIL is identifying locations, and once a site is finalised, the joint venture company can be formed and work can begin. The signing of the agreement by the end of the financial year is the milestone to watch.
Frequently Asked Questions
How much will the NLC India nuclear plant cost?
Up to Rs 35,000 crore, based on the current cost of nuclear power projects of around Rs 20 to 25 crore per MW.
When will the joint venture agreement be signed?
Acharya said it is expected to be signed by the end of this financial year, after which the joint venture company will be formed.
How much nuclear power capacity does India have now?
India has 8.78 GW across 24 commercial reactors run by NPCIL, and the government aims for about 22 GW by 2031-32 and 100 GW by 2047.